Skip to main content

Ref ID 387e0a7*

 Container

Contains 1 Result:

As Builts, Fire Alarm System (see container summary), Tri Signal Integration, 2004-05-12

 Item — Container: Ref ID 387e0a7*
Scope and Contents From the Collection:

The campus multi-phase site development and infrastructure strategy includes: Phase 1 - site clearance, rough grading, and underground utility work plus construction of the central utility plant. [Completed in 2005]. Phase 2 - completion of the central utility plant, installation of a thermal energy storage tank and street paving. [Completed in 2005] Phase 3 - site finishes, such as pedestrian paving, landscaping, lighting and a portion of street paving. [Completed in 2005]

Dates: 2004-05-12