As Builts, Fire Alarm System (see container summary), Tri Signal Integration, 2004-05-12
Scope and Contents
The campus multi-phase site development and infrastructure strategy includes: Phase 1 - site clearance, rough grading, and underground utility work plus construction of the central utility plant. [Completed in 2005]. Phase 2 - completion of the central utility plant, installation of a thermal energy storage tank and street paving. [Completed in 2005] Phase 3 - site finishes, such as pedestrian paving, landscaping, lighting and a portion of street paving. [Completed in 2005]
Dates
- Creation: 2004-05-12
Extent
10 Sheets (Central Plant: Group F, Division 2 Telecommunications: Group B Utility Tunnel: Group F, Division 2 Potable Water Pump Station: Group F, Division 2) ; 30" x 42"
Language of Materials
From the Class: English
Physical Location
Castle Warehouse, Behind Map Case 1
Repository Details
Part of the University of California, Merced, Design and Construction Archives Repository