Source Test Report for Compliance Testing of Five Natural Gas-Fired Boilers, TRC Environmental, 2005-02-01
File — Container: Ref ID ref264_qx6
Scope and Contents
From the Collection:
The campus multi-phase site development and infrastructure strategy includes: Phase 1 - site clearance, rough grading, and underground utility work plus construction of the central utility plant. [Completed in 2005]. Phase 2 - completion of the central utility plant, installation of a thermal energy storage tank and street paving. [Completed in 2005] Phase 3 - site finishes, such as pedestrian paving, landscaping, lighting and a portion of street paving. [Completed in 2005]
Dates:
2005-02-01