Skip to main content

Ref ID ref266_147

 Container

Contains 1 Result:

Central Plant and Potable Water Pump Shaft Alignment Report

 File — Container: Ref ID ref266_147
Scope and Contents From the Collection:

The campus multi-phase site development and infrastructure strategy includes: Phase 1 - site clearance, rough grading, and underground utility work plus construction of the central utility plant. [Completed in 2005]. Phase 2 - completion of the central utility plant, installation of a thermal energy storage tank and street paving. [Completed in 2005] Phase 3 - site finishes, such as pedestrian paving, landscaping, lighting and a portion of street paving. [Completed in 2005]

Dates: Between 2002 and 2006