Drawings, Bid Package: D-Site Utilities, ARUP, 2005-03-10
Scope and Contents
The campus multi-phase site development and infrastructure strategy includes: Phase 1 - site clearance, rough grading, and underground utility work plus construction of the central utility plant. [Completed in 2005]. Phase 2 - completion of the central utility plant, installation of a thermal energy storage tank and street paving. [Completed in 2005] Phase 3 - site finishes, such as pedestrian paving, landscaping, lighting and a portion of street paving. [Completed in 2005]
Dates
- Creation: 2005-03-10
Extent
69 Sheets ("Site Development and Infrastructure Part 2 - D- Site Utilities") ; 18" x 24"
Language of Materials
From the Record Group: English
Physical Location
Castle Warehouse, Behind Map Case 1
Repository Details
Part of the University of California, Merced, Design and Construction Archives Repository