Shop Drawings, Central Plant Concrete Framework Submittal #3003-3100-1, Conco Cement Co., 2004-01 - 2004-03
Scope and Contents
The campus multi-phase site development and infrastructure strategy includes: Phase 1 - site clearance, rough grading, and underground utility work plus construction of the central utility plant. [Completed in 2005]. Phase 2 - completion of the central utility plant, installation of a thermal energy storage tank and street paving. [Completed in 2005] Phase 3 - site finishes, such as pedestrian paving, landscaping, lighting and a portion of street paving. [Completed in 2005]
Dates
- Creation: 2004-01 - 2004-03
Extent
32 Sheets ; 42" x 30"
Language of Materials
From the Record Group: English
Physical Location
Castle Warehouse, South Drawing Bay, Unspecified
Repository Details
Part of the University of California, Merced, Design and Construction Archives Repository