BP4 Submittals 15365 through 16271, 2004
Scope and Contents
The campus multi-phase site development and infrastructure strategy includes: Phase 1 - site clearance, rough grading, and underground utility work plus construction of the central utility plant. [Completed in 2005]. Phase 2 - completion of the central utility plant, installation of a thermal energy storage tank and street paving. [Completed in 2005] Phase 3 - site finishes, such as pedestrian paving, landscaping, lighting and a portion of street paving. [Completed in 2005]
Dates
- Creation: 2004
Extent
3.3 Linear Feet (Inventory: 15365: FM 200 Fire Suppression 15400: Hose Bibb Data 15480: Water Heater Drawings w/ Pump Type 15540: Base Mounted Pumps Data 15545: Chemical Water Treatment System Drawings 15555: Boiler System Assembly Drawings 15556: Hot Water Boiler Assembly Drawings 15575: Layout of Breechings 15260: Water Chillers Drawings 15640: Induced Draft Cooling Tower Drawings 15660: Sidestream Filtration Packages for Closed Systems Drawings 15850: Air Handling Drawings 15860: Centrifugal Fans and Accessories Data 15890: Ductwork Layout Drawings 15910: Flexible Connections Data 15950: Refrigeration 15990: Mechanical 16050: Upper Level 16060: Rod Electrode Data 16070: Supports Systems Layout Drawings 16075: Nameplates Data 16080: List of Equipment to be Commissioned 16120: Building Wire and Cable Conductor 16131: Conduit Schedule 16132: List of Box Construction, Size and Finish 16133: Surface Raceways Data 16134: Drawings showing Tray Type, Dimensions, Support Points, and Finishes 16140: Wall Switches Data 16230: Engine Generator System Drawings 16271: Distribution Transformers Drawings)
Language of Materials
From the Record Group: English
Location
Castle Warehouse, Cabinet 4, Drawer 3
Repository Details
Part of the University of California, Merced, Design and Construction Archives Repository