Bid Package 6, 100% Construction, Plans, 2003-10-03

 Item — Container: Ref ID ref246_9v7

Scope and Contents

From the Collection:

The campus multi-phase site development and infrastructure strategy includes: Phase 1 - site clearance, rough grading, and underground utility work plus construction of the central utility plant. [Completed in 2005]. Phase 2 - completion of the central utility plant, installation of a thermal energy storage tank and street paving. [Completed in 2005] Phase 3 - site finishes, such as pedestrian paving, landscaping, lighting and a portion of street paving. [Completed in 2005]

Dates

  • Creation: 2003-10-03

Extent

222 Sheets ; 18" x 26"

Language of Materials

From the Record Group: English

Location

Castle Warehouse, Map Case, Drawer 9

Repository Details

Part of the University of California, Merced, Design and Construction Archives Repository