Ref ID 359de67*
Container
Contains 1 Result:
CTS Fence Executed Agreement, Otto Construction, 2016-01
File — Container: Ref ID 359de67*
Scope and Contents
From the Collection:
The project completed key phases of work related to the Section 404 permit conditions including: 1) construction of a dirt perimeter road to improve access to the outer areas of the campus and community; 2) construction of appropriate boundary fencing between the campus and preserve lands; 3) mass grading to improve storm water management; 4) construction of a kit fox bridge; and 5) salvage of impacted wetland soils. ENTIRE CAMPUS
Dates:
2016-01