Structural Calculations, Eric Picciano, P.E.
Scope and Contents
The project completed key phases of work related to the Section 404 permit conditions including: 1) construction of a dirt perimeter road to improve access to the outer areas of the campus and community; 2) construction of appropriate boundary fencing between the campus and preserve lands; 3) mass grading to improve storm water management; 4) construction of a kit fox bridge; and 5) salvage of impacted wetland soils. ENTIRE CAMPUS
Dates
- Creation: Summer 2013
Extent
2 Volumes (2 email correspndence, subject: Review of plans for Kit Fox Bridge 20120111 1 Kit Fox Bridge Structural Calculations plans 20120112 2 Kit Fox Bridge Structural Calculations plans 20120109 3 Shop Drawings by Eric Picciano, P.E.)
Language of Materials
From the Class: English
Physical Location
Castle Warehouse, Large Drawing Cubbies, Cubby 22
Repository Details
Part of the University of California, Merced, Design and Construction Archives Repository