Landscaping & Irrigation Improvements Operating & Maintenance Instructions
Scope and Contents
The campus multi-phase site development and infrastructure strategy includes: Phase 1 - site clearance, rough grading, and underground utility work plus construction of the central utility plant. [Completed in 2005]. Phase 2 - completion of the central utility plant, installation of a thermal energy storage tank and street paving. [Completed in 2005] Phase 3 - site finishes, such as pedestrian paving, landscaping, lighting and a portion of street paving. [Completed in 2005]
Dates
- Creation: December 2006
Extent
1 volume (Volume 1 of 1 (4 copies))
Language of Materials
From the Class: English
Physical Location
Promenade, Suite M, Conference Room Cabinet 9
Repository Details
Part of the University of California, Merced, Design and Construction Archives Repository