Bid Packages A-D (see container summary)
Scope and Contents
The campus multi-phase site development and infrastructure strategy includes: Phase 1 - site clearance, rough grading, and underground utility work plus construction of the central utility plant. [Completed in 2005]. Phase 2 - completion of the central utility plant, installation of a thermal energy storage tank and street paving. [Completed in 2005] Phase 3 - site finishes, such as pedestrian paving, landscaping, lighting and a portion of street paving. [Completed in 2005]
Dates
- Creation: December 2006
Extent
7 Volumes (Bid Package A, Earthwork, Granite Construction, volume 1 Bid Package A, Earthwork, Granite Construction, volume 2 Bid Package B, Site Electrical (West), Rex Moore Electrical, volume 1 Bid Package B, Site Electrical (West), Rex Moore Electrical, volume 2 Bid Package C, Site Electrical (East), Collins Electrical, volume 1 Bid Package C, Site Electrical (East), Collins Electrical, vol. 2 Bid Package D, Site Utilities, Granite Construction, 1 of 2 volumes )
Language of Materials
From the Class: English
Location
Castle Warehouse, Cabinet 2, Drawer 4
Repository Details
Part of the University of California, Merced, Design and Construction Archives Repository