6_Construction Administration
Class
Scope and Contents
From the Collection:
The project completed key phases of work related to the Section 404 permit conditions including: 1) construction of a dirt perimeter road to improve access to the outer areas of the campus and community; 2) construction of appropriate boundary fencing between the campus and preserve lands; 3) mass grading to improve storm water management; 4) construction of a kit fox bridge; and 5) salvage of impacted wetland soils. ENTIRE CAMPUS
Dates
- Creation: Summer 2013
Extent
20 Linear Feet (At this writing this number is just an estimate, 3.24.14, JT.)
Language of Materials
English
Repository Details
Part of the University of California, Merced, Design and Construction Archives Repository